Herunterladen Inhalt Inhalt Diese Seite drucken

Warming Up The Machine; Electrical Connection - Optimum OPTImill F 80 Betriebsanleitung

Inhaltsverzeichnis

Werbung

Verfügbare Sprachen

Verfügbare Sprachen

OPTIMUM
M A S C H I N E N - G E R M A N Y
breaker of the engine of coolant pump against each other.
WARNING!
Swapping the phases must be performed by a qualified electrician!
Check all oil levels and filling levels of lubricants in the reservoirs.
Perform a safety test.
3.9.1

Warming up the machine

ATTENTION!
If the CNC-machine and in particular the milling spindle is immediately operated at
maximum load when it is cold it may result in damages.
If the machine is cold such as e.g. directly after having transported the machine it
should be warmed up at a spindle speed of only 500 1/min for the first 30 minutes.
3.9.2
Save data function
The CNC control only provides a "transient working memory" losing its contents at the latest
after 3 weeks.
For this reason it is imperatively necessary to perform a data backup after commissioning the
machine respectively the machine control.
The "Save data" function saves the contents of the volatile memory into a nonvolatile memory
area.
Requirement: There is no program currently executing.
Do not carry out any operator actions while the data backup is running!
The NC and PLC data are backed up.
To call the saved data, follow these steps:
1. Press the <SELECT> key while the control system is booting.
2. In the setup menu, select "Reload saved user data".
3. Press <INPUT>.
INFORMATION
Data that have been backed up can be called again by selecting "System" > "Start-up" >
"Power-up with saved data"!
3.9.3

Electrical connection

Check the fusing (fuse) of your electrical supply according to the technical instructions
regarding the total connected power of the milling machine.
Firmly connect the machine.
CAUTION!
Install the connection cable of the machine in such a way that people will not stumble
over it.
Please verify if the type of current, voltage and protection fuse correspond to the values speci-
fied. A protective earth ground wire connection must be available.
Main Fuse 16A.
Due to the design, the leakage current is greater than 3,5 mA. We ask for due attention while
executing machine tests within the framework of industrial safety guidelines.
GB
F80 | F105
Page 242
®
Translation of the original instructions
Assembly and commissioning
Version 1.1.2 dated 2019-05-07

Werbung

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Optimill f 150

Inhaltsverzeichnis