Terminal
Signal
number
Insufficient water switch,
contact 32/34. Lead the cable
34
E2
of the insufficient water switch
through the cable gland and
connect at the terminals
6.5.2
RS-485 interface
6.5.2.1 Connecting the RS-485 interface
Connect the interface as follows:
1.
For connecting the interface use only a cable with these properties:
–
LJYCY (TP), 4 × 2 × 0.8, maximum overall bus length 1000 m.
2.
Use a shielded cable to connect the interface to terminals 29, 30, 31 of the
main board in the control cabinet.
–
For connecting the interface, 6.5 "Electrical connection", 33.
3.
When using the device with a control centre not supporting an RS-485
interface (RS-232, for example), you must use a corresponding adapter.
6.6
Installation and commissioning certificate
Data shown on the type plate:
Type:
Manufacturing number:
This device has been installed and commissioned in accordance with the
instructions provided in the operating manual. The settings in the controller
match the local conditions.
Note!
When any factory-set values of the device are changed, you must enter
this information in the Maintenance certificate, 9.3 "Maintenance
certificate ", 44.
For the installation
Place, date
Company
For the commissioning
Place, date
Company
7
Commissioning
Note!
Confirm that installation and start-up have been carried out correctly
using the installation, start-up and maintenance certificate. This action is
a prerequisite for the making of warranty claims.
–
Have the Reflex Customer Service carry out commissioning and
the annual maintenance.
7.1
Checking the requirements for commissioning
The Servitec will be ready for initial commissioning when the tasks described in
the "Installation" chapter have been completed.
•
The Servitec has been mounted.
•
The connections of the Servitec to the system have been created and plant
system pressure maintenance is operational.
–
Degassing line to the facility system.
–
Degassing line from the facility system.
•
The water-side connection of the Servitec to the make-up has been
created and is operational, if automatic make-up is required.
•
The connection pipes of the Servitec have been purged and cleaned of
welding residue and dirt before commissioning.
•
The entire facility system is filled with water and all gases have been
vented in order to ensure a circulation through the entire system.
•
The electrical connection has been created according to applicable
national and local regulations.
Function
Wiring
Pre-wired
P
0
P
SV
Signature
Signature
Vacuum spray degassing — 01.04.2022-Rev. D
7.2
Setting the minimum operating pressure for
Magcontrol
The "p
" minimum operating pressure is determined by the location of the
0
Servitec.
Description
p
Static pressure
st
p
Minimum operating pressure
0
p
Initial pressure (cold water filling
a
pressure)
p
Final pressure
e
p
Safety valve actuating pressure
Sv
The calculation of the minimum operating pressure can be directly calculated
and saved during initial commissioning using the Reflex Control Smart app for
configuration. Please always check the correct inlet pressure of the expansion
vessel in the system. Proceed as follows:
1
In the app, set the controller to "Magcontrol".
2.
Determine the "P0" minimum operating pressure of the device relative to
the "p0" initial pressure of the expansion vessel.
•
The device is installed at the same level as the expansion vessel
(∆h
= 0).
st
–
P
= p0*
0
•
The device is installed at a lower level than the expansion vessel.
–
= p0 + ∆h
P
/10*
0
st
•
The device is installed at a higher level than the expansion
vessel.
–
= p0 - ∆h
P
/10*
0
st
p0 in bar, ∆h
*
in m
st
Note!
The safety valve actuating pressure must always be observed for the
target value of the Servitec
(see calculation formula).
Commissioning
Calculation
= static head (h
)/10
st
= p
+ 0.2 bar (recommended)
st
= p
+ 0.3 bar
0
≤ p
≤ 5.0
- 0.5 bar (for p
Sv
Sv
bar)
≤ 5.0
= p
+ 1.2 bar (for p
0
Sv
bar)
English — 35