Initialization run
◼ When commissioning the control unit for the first time
Carry out an initialization run in the following circumstances:
◼ When the number of connected drives is changed
◼ When resetting the control unit to factory settings
◼ Connecting 2 - 8 control units in order to move drives synchronously
◼ Respective error message
Carrying out initialization
Personnel:
◼ All drives and controls are connected to each other.
Prerequisite:
1.
Unplug the mains plug and wait 30 s.
2.
Press and hold the
⇨ The LED display flashes red and green alternately.
3.
Plug in the mains plug and wait approximately 5 s.
4.
Release the
5.
Press and hold the
Control RK MultiControl II duo/RK MultiControl II quadro
page 281.
In order to be able to move the drives, the initialization run must
be completed.
◼ User
The system must be de-energised for at least 30 s.
buttons at the same time.
buttons.
button until all drives have moved into the lower final position.