Electrical dangers
DANGER!
Electrical hazards are marked by the symbol opposite.
Work in these areas may only be carried out by trained personnel with the
appropriate authorisation.
Commissioning steps:
1.
Activate pump (electrical connection / control system).
2.
Check function of the pump.
3.
Check medium carrying components for leak tightness.
Fig. 8: Tighten the pump head screws.
4.
CAUTION!
The four pump head screws (Pos. 1) are then to be tightened using a
torque of 4 Nm!