11.3.1

Gear oil draining

 Manually unscrew gear vent screw (pos. 1).
 Put a suitable collecting basin (min. volume 0.9 l) underneath the locking nut (pos. 3).
 Loosen locking nut with a socket for wrenches (SW 19) and unscrew it carefully.
 Let the running out oil drain off into the collecting basin.
 Screw-in locking nut with new O-ring (NBR  9 x 2 mm) and tighten it up.
11.3.2

Gear oil top up

 Fill new gear oil into the aperture for the gear vent screw (pos. 1) by using an
appropriate funnel (filling volume approx. 0.8 l).
 Check oil level on oil-level gauge glass (pos. 2), min. and max. oil level see Fig. 11.5,
and rectify if necessary.
NOTE
11.4

Motor replacement

11.4.1

Disassembly

 Open the terminal box (pos. 2) of the motor (pos. 1).
 Branch off the mains connection cable in the terminal box
 Loosen cable connections (pos. 3) and carefully pull out the cable
 The 4 motor attaching screws (pos. 4) have to be loosened crosswise and unscrewed.
 Pull off motor towards the top. In case of stiffness, two screw drivers, which are carefully
pulled into the water drip grooves (pos. 4) of the housing flange, can be used so that the
motor can be raised straight upwards. The motor should not be set on its edges.
11.4.2

Installation

 Clean splined shaft and housing flange, and moisten motor and splined shaft with
Teflon fat.
 Place motor shaft right onto splined shaft and pull softly until flange is reached. Do not
set motor on its edges.
 Turn the motor in a way that the terminal box points straight forward into the direction of
the stroke adjustment knob.
 Place attachment screws (pos. 4) and tighten them crosswise (tightening torque 12 Nm).
 Mains connection cable and (if necessary) connection cable to the pump housing may
then be reconnected
 Re-establish mains voltage supply.
CAUTION
After 24 hours attaching screws have to be tightened up by 12 Nm.
417101799_EMP_IV_E60.docx
Only use gear oil of type L-CKT 320 that meets the ISO 6743 requirements.
Dispose correctly of waste oil!
Fig. 11.6
Motor replacement
Pos.
1
2
3
4
5
Before replacing the motor the plug has to be
WARNING
disconnected from the mains. The device has to
be prevented from reclosing.
Description
Motor
Terminal box cover
Cable connections
Motor attaching screws
water drip groove
- 115 -
Rev. 11-10.19

Quicklinks ausblenden:

Werbung

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Elados emp iv e60Elados emp iv e60 plus

Inhaltsverzeichnis