DANGER
Procedures
1. Inspect the foundation that the
device is sited on
2. Inspect the operating area,
including the raised floor
Bosch Power Tec GmbH
9

Commissioning report

9.1

Safety instructions

Risk of fatal injury due to residual voltages
When the central inverter is shut down using the On/Off switch, voltage is
still present at the AC and DC connections and in the internal control
system. After shutting down the system using the On/Off switch, the
capacitors of the central inverter may still carry a residual charge. Residual
voltages inside the device can result in fatal surges.
Open all external disconnectors and secure them against being switched
back on
After de-energising the device, always wait for an additional 15 minutes
before touching any components
Check that the device is de-energised using a measuring instrument, in
accordance with applicable guidelines. The measuring instrument used
must be approved for at least protection class CAT II 1000 V or CAT III
600 V (in accordance with IEC EN 61010-1).
9.2

Preparations

Materials required
The appropriate, tested measuring equipment
Please note the following here:
– Incorrect connections can cause voltages > 1000 VDC
Anemometer
Differential pressure measuring equipment
Prerequisites
Inspect the installation before commissioning
– Use any safety devices fitted to the device and follow any safety
instructions on the device
– Observe safety guidelines for conducting measurements on live system
and device components
– Before carrying out any measurements, read the operating manual for
the measuring equipment
9.3

Report

Desired result
The floor bears the weight of the
device.
The operating area, including the
raised floor, is free of foreign
objects and moisture.
Actual result/assessment
Commissioning report | 79
Action in case of non-compliance
– Change the installation position of
the device (Space requirement for
transport and installation (crane
operator, industrial truck driver),
p. 38)
– Clean the operating area
– Remove sand, water and other
dirt