NOTICE
Bosch Power Tec GmbH
Please note the following here:
The connector must be plugged in firmly and securely.
The fan set is installed.
5.4

Connecting the solar generator

Materials required
Torque wrench 19 mm
Cable stripping knife, insulation removal tool
M12 cable lug
Please note the following here:
– Cable lugs must be of the correct size for the cable diameters used.
– Cable lugs must be insulated on the shaft using an insulating sleeve or
shrink tubing.
– Cable lug manufacturer's specifications
Permissible tools for crimping cable lugs.
Please note the following here:
– Local regulations
– Applicable standards and directives
Prerequisites
Safety equipment installed (Required on site, p. 19)
2–8 cable leads
Each central inverter has four DC inputs.
When switching off: First de-energise the central inverter using the
disconnector in the field and then switch off the DC circuit breaker.
When switching on: Leave the DC circuit breaker of the central inverter
switched off and switch on the disconnector first. This enables you to
check whether the DC main cables are correctly connected to the DC
connection bars in the central inverter. Switch off the external
disconnector after checking. Then switch on the DC circuit breaker for the
central inverter. Now switch on the external disconnector.
Procedure
1. Remove the lower protective cover
2. Check the cable leads of the solar generator
Material damage due to unsuitable cable lugs
The cable lugs used must match the selected cable diameter, the device's
connection bar and the diameter of the threaded bolt. If unsuitable cable
lugs are used, they may work loose, thereby interrupting the flow of
current and causing material damage.
Use cable lugs of the correct size
Only crimp the cable lugs with approved tools
Do not use aluminium cable lugs
If aluminium cables are used, use aluminium-copper washers or
aluminium-copper transition cable lugs.
Installation | 51
BPT-C 200, 300, 350 | Operating manual

Werbung

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Bpt-c 300Bpt-c 350

Inhaltsverzeichnis