Commissioning

6.1

Filling out the commissioning report

Materials required
The appropriate, tested measuring equipment
Please note the following here:
– Incorrect connections can cause voltages of U
– All measuring devices and cables used must be approved for at least
protection class CAT II 1000 V or CAT III 600 V (in accordance with IEC
EN 61010-1).
Inspect the installation before commissioning.
Please note the following here:
Safety devices and safety instructions on the device
Safety guidelines for conducting measurements on live systems and
components
The operating manual of the measuring equipment
Before commissioning, inspect the configuration of the system and the
cable routing.
If the necessary documents are missing, contact the operator of the
photovoltaic system.
Risk of fatal injury due to residual voltages
When the central inverter is shut down using the On/Off switch, voltage is
still present at the AC and DC connections and in the internal control
system. After shutting down the system using the On/Off switch, the
capacitors of the central inverter may still carry a residual charge. Residual
voltages inside the device can result in fatal surges.
Open all external disconnectors and secure them against being switched
back on
After de-energising the device, always wait for an additional 15 minutes
before touching any components
Check that the device is de-energised using a measuring instrument, in
accordance with applicable guidelines. The measuring instrument used
must be approved for at least protection class CAT II 1000 V or CAT III
600 V (in accordance with IEC EN 61010-1).
Procedure
1. Filling out the commissioning report (Commissioning report, p. 79)
Please note the following here:
Measured data must comply with the following:
– Applicable standards and directives
– Power supply company requirements
– Technical specifications of the device (Technical specifications, p. 83)
The report is filled out.
6.2
Commissioning
Before commissioning, all LED indicators below the display are off.
Commissioning | 65
> 1000 V.
DC
BPT-C 200, 300, 350 | Operating manual