50 | Installation
BPT-C 200, 300, 350 | Operating manual
5.2

Requirements

Safety equipment installed (Required on site, p. 19)
Mains voltage is within the specified limits (Technical specifications, p. 83)
Before starting any work:
– De-energise the device and secure it against being switched back on
– Ensure that the device is fully de-energised
– Ensure that the connections are fully de-energised
– Cover or shield any adjacent live components
Please note the following here:
– The power source of photovoltaic systems is always active during
daylight
Depending on the selected installation:
– On raised floors: Assembled base panels: Device takes in air from below.
– On the floor: All base panels are removed: Device takes in air from the
front and the side of the operating area.
Transport rails removed and screws on the transport rails undone
Cable leads for the connections in the operating area are provided on site
in the right length and size (replace cable leads if there is any damage)
Cable strain relief (each central inverter has a cable support rail. Due to
large bending radii of the lines and cables, it can be necessary to use
external cable strain relief. The cable strain relief must only be provided
with appropriately approved components.)
5.3

Installing the fan set

Materials required
Four M6 nuts (included in the scope of delivery)
Procedure
1. Top of the device: Secure the fan set
5.1:
Top of the device with fan-set position
[1]
Fan set
[2]
Fan set connector
2. Plug in the fan set connector.