Before Switching On - Lenze 8200 vector Montageanleitung

Vorschau ausblenden Andere Handbücher für 8200 vector:
Inhaltsverzeichnis

Werbung

Verfügbare Sprachen

Verfügbare Sprachen

Show/Hide Bookmarks
Note!
l
l
Check the following to avoid damage to persons or material...
...before the mains voltage is connected:
Completeness, short circuit and earth fault
l
"Emergency-off" function of system
l
Motor connection (star/delta) must be adapted to output voltage of controller.
l
If you do not use a function module ensure that the FIF cover is mounted properly (as
l
delivered).
If the internal voltage supply is connected, for instance, to X3/20 of the standard-I/O, terminals
l
X3/7 and X3/39 must be bridged.
... the most improtant drive parameter settings before the controller is enabled:
Are the parameters needed for your application set correctly?
l
– e. g. configuration of analog and digital inputs and outputs
L
Do not change the switch-on sequence.
In the event of an error during commissioning please see the chapter "Fault
detection and elimination".
EDK82EV222 DE/EN/FR 6.0
Commissioning

Before switching on

7
31