Procedure for commissioning
The following work must be carried out in the specified order:
Connect the station to the outflow
1.
Ä Chapter 7.3 'Connect station to outflow' on page 41
Bleed the backflow preventer
2.
Ä Chapter 7.4 'Bleed the backflow preventer' on page 41
Bleed the dosing pump
3.
Ä Chapter 7.5 'Bleed dosing pump' on page 42
Set the dosage
4.
Ä Chapter 7.6 'Set the dosage' on page 44
Check the station for leaks
5.
Ä Chapter 7.7 'Check station for leaks' on page 45
Connect the station to the disinfectant supply
6.
Ä Chapter 7.8 'Connect station to the disinfectant supply' on page 46
7.3
Connect station to outflow
For initial commissioning and for maintenance and bleeding, thestation on the media
outlet should be connected to the drainage system.
Alternatively, water escaping while work is being carried out can be collected in
a sufficiently large collection vessel, then disposed of in an outflow drain.
Prerequisite:
Main tap (water supply) is closed.
n
Connect a hose to the media outlet ( Fig. 2 ,
1.
Route the hose into the drainage system or into a sufficiently large collection vessel.
2.
7.4
Bleed the backflow preventer
Manufacturer documentation
Further information can be found in the manufacturer documentation
of the respective supplier component (see
C 'Component operating manuals' on page 102 ).
41
) on thestation.
8
Ä Appendix
MAN048969, Ver. 5-05.2024
Start-up