Herunterladen Diese Seite drucken

ECOLAB EcoUp Betriebsanleitung Seite 133

Werbung

Verfügbare Sprachen
  • DE

Verfügbare Sprachen

  • DEUTSCH, seite 1
Installation example 5
Installation example 6
Installation example 7
1
Connection of the suction and pressure tubes (dosing lines)
CAUTION!
When connecting the suction and charge pipe, make sure that the O-rings are
mounted on the connections in order to achieve the necessary sealing.
To protect the metering system, we strongly recommend the use of a suction
lance with an empty signal system and mud guard from our accessory
programme. The empty signal feature causes the pump to cut off if the medium
in the container drops below a certain level.
Suction lines should be kept as short as possible.
Long and intertwined suction tubes can lead to accumulation of air in the
system.
The suction height must be max. 2 m and the flow rate max. 0.3 m/s.
The suction line must always be installed sloping upwards towards the
metering pump.
A metering monitoring device, such as an oval gear meter
monitor, must be installed into the metering line downstream of the overflow
valve and upstream of a pressure control valve or metering valve.
35
Assembly and connection
, or flow
MAN049656 Rev. 3-01.2024

Werbung

loading