7.2.4.5 Installing the metering monitoring
NOTE
= Input metering monitoring function with potential-free contact with selection input „pulse"
2
+
4
at configuration / metering monitoring (see chapter 10.3.13).
PIN
Assignment
2
Relay input
GND (┴)
4
1 +2
+
4
= Input metering monitoring function with electronic switch (NPN) with selection input
„pulse" at configuration / metering monitoring (see chapter 10.3.13).
PIN
Assignment
1
5 V, DC
2
Relay input
GND (┴)
4
or
3
+
4
= Input metering monitoring function with potential-free contact with selection input
„metering lock" at configuration / metering monitoring (see chapter 10.3.13).
PIN
Assignment
3
Relay input
GND (┴)
4
1 +3
+
4
= Input metering monitoring function with electronic switch (NPN) with selection input
„metering lock" at configuration / metering monitoring (see chapter 10.3.13).
PIN
Assignment
1
5 V, DC
3
Relay input
GND (┴)
4
7.2.5
Connector assignments of slot III (4-terminal) output for alarm and stroke signal
Fig. 7.22
Connector assignments of slot III (4-terminal) output for alarm and stroke signal
Remove the protective cap
Mount the connector plug according to the connector assignment.
WARNING
417101441_EMP_III_E60.docx
The metering monitoring function must be activated in menu first. The selection must also
be made of whether the pins
used for the metering monitoring input (see chapter 10.3.13).
Conductor coloring
Pin
(cable connection)
1
brown
2
white
3
blue
4
black
(plug assignments: see also chapter 14.5.3)
Only use a connector plug from our product range! (included in the delivery scope)
(input "pulse") or
2+4
3+4
Fig. 7.21 Installing the metering monitoring
Assignment
Output low-level warning, empty report and fault (+)
Output low-level warning, empty report and fault (-)
Output stroke signal (+)
Output stroke signal (-)
- 84 -
(input "metering lock") should be
Rev. 12-08.18