3.2

Installation and assembly

3.2.1

Requirements regarding the installation site

Organize the working area around the geared drill according to the local safety regulations.
INFORMATION
In order to attain good functionality and a high processing accuracy as well as a long service life
of the machine, the place of installation should fulfil certain criteria.
Please observe the following points:
The device must only be installed and operated in a dry and well-ventilated place.
Avoid places nearby machines generating chips or dust.
The installation site must be free from vibrations also at a distance of presses, planing
machines, etc.
The substructure must be suitable for the geared drill. Also make sure that the floor has suf-
ficient load bearing capacity and is level.
The substructure must be prepared in a way that possibly used coolant cannot penetrate
into the floor.
Any parts sticking out such as stops, handles, etc. have to be secured by measures taken
by the customer if necessary in order to avoid endangerment of persons.
Provide sufficient space for the personnel preparing and operating the machine and trans-
porting the material.
Also make sure the machine is accessible for setting and maintenance works.
Provide for sufficient backlight (Minimum value: 500 lux, measured at the tool tip). At lower
illumination intensities, additional illumination has to be ensured e.g. by means of a sepa-
rate workplace lamp.
INFORMATION
The main switch of the geared drill must be freely accessible.
3.2.2

Assembly

WARNING!
Danger of crushing and overturning.
The geared drill must be installed by at least 2 people.
INFORMATION
The geared drill is delivered pre-assembled.
3.3

Installation

Check the horizontal orientation of the base of the geared drill with a spirit level.
Check that the foundation has sufficient floor-load capacity and rigidity. The total weight

amounts:
Total weight [kg] on page 86
Position the geared drill on the intended foundation.
Fix the geared drill in the provided through-holes on the machine foot.
WARNING!
The condition of the underground and the fixing type of the machine foot to the
underground must be in a way that it can bear the loads of the geared drill. The
underground must be level. Check if the underground of the geared drill is level using a
spirit level.