4.1. LIFTING OF THE MACHINE

The lifting and transport operations have to be carried on with means suitable for the weight of the machine
and by personnel trained for this kind of maneuver.

4.2. LIFTING OF THE ROTODENT

If the machine is supplied closed, connect it only as indicated in the figure to the two
suitable side hooks, during this operation the machine shall not be lifted for more
than 200 mm from the ground.
Do not connect the machine to the central hook if it is closed. This may cause
the overturning of the machine itself in that its barycentre is placed above the
connection point.
If the machine is supplied open, connect it to the central hook, as indicated in the
figure, and perform the transportation, during this operation the machine shall not be
lifted for more than 200 mm from the ground.

4.3. MACHINE WITH DISASSEMBLED ROLLER

If the machine is supplied with the roller disassembled, it is necessary to
perform the assembling of the same. Pay attention to the instability of the
machine without the roller.
Keeping the machine lifted with proper means apply it to the three points of the tractor
locking the piston pins by means of the suitable bolts.
Verify that everything is perfectly connected and place the machine onto the ground,
carefully.
Connect the roller as indicated in the figure by means of a proper lifting mean and by
keeping it stable without lifting it from the floor, proceeds as indicated in paragraph 4.4
Copyright ©2009 della Alpego spa® - All rights are reserved. Reprinting or unauthorized use of this manual is strictly forbidden without written permission by Alpego spa

4. INSTALLATION

Old Cod.D03214
Q00A00017 R.23
INSTALLATION
- 15

Quicklinks ausblenden:

Werbung

loading