5.7 ENS Test

Configuration
Extended
XModem Update
Clear data logger
Numerical list
ENS-Test
F1-Menue
Note:
Carrying out the ENS Test:
Set P0900 to "1"  starts the ENS test
P0901 shows the progress of the ENS test
P0908 informs about the frequency ramp (in mHz/s)
P0902 shows the development of the simulated frequency
P0910.00 shows the time measured until the lower frequency limit is reached
P0910.01 shows the time measured until the upper frequency limit is reached
P0903.00 shows the frequency value having caused turnoff at the lower limit
P0903.01 shows the frequency value having caused turnoff at the upper limit
P0909 informs about the voltage ramp (in mV/s)
P0904 shows the development of the simulated voltage
P0910.02 shows the time measured until the lower voltage limit is reached
P0910.03 shows the time measured until the upper voltage limit is reached
P0905.00 shows the voltage value having caused turnoff at the lower limit
P0905.01 shows the voltage value having caused turnoff at the upper limit
ENS test status list:
0
Initializing / ready for start
1 ... 3
Frequency test at the lower frequency limit
42
ENS-Test
P0900
D0901
P0908
D0902
D0910.
00
F1
.
01
F1-Menue
ESC
ENS-Test
D0910.
00
F1
.
01
D0903.
00
ESC
D0903.
01
P0909
D0904
F1-Menue
If the ENS test is carried out while the device is disconnected from power
supply, there will be no result. First restart the device.
P0900.
00
0
Start ENS-Test
0
50
0
50
0
F1
0
F1-Menue
ESC
D0904.
00
0
Test result of voltage
0
test
0
230
0
11500
Volt
F1
230
F1-Menue
ESC
748.508 | Z01 | 2013-06-10