8. Commissioning
NOTE
Connecting multiple solar inverters
via RS485
► If multiple solar power inverters are
to be connected via RS485, select
a different ID for each inverter. This
ID will also be used later to identify
each solar power inverter when
loading settings or transferring data.
► Set the termination resistor to "ON"
at the last solar power inverter in
the row.
18. Select Continue and press the E
R S 4 8 5
T e r m i n a t i o n :
C o n t i n u e
- - - - - - - - - - - - - - - - - - -
→ The last menu is displayed.
E N T E R
t o c o n f i r m
E S C
t o s e l e c t a g a i n
19. Press the E
button to finish commissioning.
ntEr
þ
Commissioning is now finished.
30
button.
ntEr
O f f
8.5
Commissioning by loading the settings
from another solar power inverter
ATTENTION
The data is loaded via the USB interface.
Using a USB stick reduces the degree of
protection.
NOTE
► The STUP_###.CFG file must be in the
main directory of the USB stick. The
### characters represent the RS485 ID
of the solar power inverter from which
the data is to be loaded, for example
"001".
8.5.1

Brief overview of the commissioning steps

► Set the display language
► Load the data from a USB stick
After loading you can decide whether or not to edit the data.
In this case, the commission steps are the same as those
for the standard commissioning (depending on the grid).
The commissioning process is shorter if you adopt the data
without making changes:
► Set the date and time
► Set up the RS485 communication
8.5.2
Detailed description of the commissioning
steps
1.
Save the settings from the other solar power inverter if
you have not already done this, see
tings", p. 47.
2.
Check all connections and cables for damage and cor-
rect seating. Correct the installation if necessary.
3.
Switch on the DC switch.
→ The startup process of the solar power inverter
begins.
After the startup process and the automatic self-test
the initial commissioning procedure of the solar power
inverter starts and the Installation menu is displayed.
4.
Select a language for the display.
I n s t a l l a t i o n
- - - - - - - -
- - - - - - - - - - -
L a n g u a g e :
E n g l i s h
C o n t i n u e
Configurable parameters
Display text
Designation
Language
Language
Operation and installation manual for SOLIVIA 11 EU G4 TR
"11.4 Saving set-
Description
The display language.
Czech | Danish | Dutch | Eng-
lish | French | Italian | Portu-
guese | Romanian | Slovak |
Slovenian | Spanish

Werbung

Kapitel

Inhaltsverzeichnis
loading

Inhaltsverzeichnis