Fig. 80 Circuit breaker F1
Fig. 81 Front view
18. Close the restrictor screw (Fig. 77/2) by 2 turns.
19. Guide the vent hose (Fig. 75/6) into the funnel.
20. Switch on automatic cutout F1 (Fig. 80/1).
21. Leave the chiller pump switched on until the formation of bubbles in the vent hose (Fig. 75/6)
stops.
Suprasetter 106 – Installation
11. Make automatic cutout F1 (Fig. 80/1) for the
chiller accessible on the Suprasetter. To do
so, remove the panel (upper right).
12. Switch on the Suprasetter with the power
switch. Do not press the operating button if
you are prompted to do so on the screen. The
Suprasetter activates the chiller.
The pump in the chiller pumps the coolant into the
circuit. The pump will then automatically switch
off.
13. Switch off automatic cutout F1 (Fig. 80/1).
14. Prepare another 2 liters of coolant using the
mixture ratio mentioned above. Carefully fill
the blend into the funnel until the liquid level
in the filler hose has reached the "Max" mark
(Fig. 81/1).
15. Switch on automatic cutout F1 (Fig. 80/1) for
the chiller on the Suprasetter. The pump in
the chiller pumps the coolant into the circuit.
The pump will then automatically switch off.
16. Switch off automatic cutout F1 (Fig. 80/1).
17. Repeat steps
13
thru
the pump no longer stops. The liquid level
must reach the "Max" mark after filling is
completed.
Installation
15
(approx. 3 times) until
85