Service and repair

10.1

Maintenance schedule

"
Please note the information on maintenance and repair from page
188 and from page 199.
Include the following activities in the maintenance schedule:
"
• Check the functionality of all protective devices in intervals not ex­
ceeding six months.
This refers to, in particular, the operativeness of the protective
conductor wiring and (if used) the ground fault protection device
and the ground fault protection resistor.
Error states must quickly release the system's main switch.
• In case of water‐cooled units: Check the cooling water circuit for
leaks and proper functioning. Corrosion or condensation may not
occur.
Use suitable cooling water additives, e.g., in order to avoid algae
growth.
• In case of air‐cooled units: remove dust and other contamination
from the air‐cooling system.
• Check terminal and clamp connections of all cables for damages
and firm sit. Replace defective parts immediately.