Hydraulic Installation

The direction of flow through the CS1000 is arbitrary. Use one connection port as the INLET
port and the other as OUTLET port.
Depending on how the CS is ordered, it features the following hydraulic connection options:
- Pipe/hose connection: The CS is connected to the hydraulic system via ports A and B
using a pipe or hose. (see section 5.1)
- Flange connection: The CS is screwed to a flange, mounting plate, manifold mount or
control block, with flow being effected through the unit via port C and D on the underside.
Determine the system pressure of the hydraulic system and see whether it is within the
permissible range for the INLET port.
The pressure in the measurement cell may not exceed

Select guidelines to a Measurement Point

6.3.1
The measurement point has to be selected so that the measured volume is taken from a
turbulent flow area, i.e. a pipe bend.
The CS has to be installed in the vicinity of the measurement point in order to a prevent
sedimentation (formation of particle deposits) in the inlet line and achieve short timed results
prevent time delayed results.
to CS
Mainflow
WRONG
Always install the measurement point in a turbulent flow area, i.e. in a pipe bend.
While installing the measurement line, make sure that no "siphon trap" is created.
WRONG
HYDAC Filtertechnik GmbH
BeWa CS1000 3247149-02j en.doc
All manuals and user guides at all-guides.com
Mainflow
Mainflow
en
Installation and Operation
100
bar.
Mainflow
to CS
OK
OK