Mechanical installation
6
Mechanical installation
16
6.1
Important precautions during
installation
S Handle the transducer with care.
S Welding currents must not be allowed to flow over the
transducer. If there is a risk that this might happen,
you must use a suitable low‐ohm connection to elec
trically bypass the transducer. HBM, for example,
provides the highly flexible EEK ground cable, which
can be screwed on above and below the transducer.
S Make sure that the transducer cannot be overloaded.
WARNING
There is a danger of the transducer breaking if it is over
loaded. This can cause danger for the operating person
nel of the system in which the transducer is installed.
Implement appropriate safety measures to avoid over
loads or to protect against the resulting dangers.
6.2
General installation guidelines
The forces to be measured must act on the transducer
as accurately as possible in the direction of measure
ment. Torsional and bending moments, eccentric load
ings and lateral forces can produce measurement errors
and can destroy the transducer if limit values are
exceeded. Interference effects must be absorbed by suit
able construction elements, whereby these elements
A3592-1.3 HBM: public
S2M