1
·
Loose two nuts on the pipe to release air
and water in cell vessel; then loose the top
retaining nut
Open cell cap, pull out the
flow rate sensor connector as
figure shows above.
Replace
new
flow
sensor with the right direction
(reverse cannot be installed);
tighten sensor with screws;
install connector as figure
shows and put back cell cap.
4.No chlorine producing or chlorine generator shutdown automatically
4.No chlorine producing or chlorine generator shutdown automatically
- Check if the power line of control box is right connected to protection socket.
-Check if the power line of control box is right connected to protection socket.
- Check the salt level in pool water.
-Check the salt level in pool water.
- Check the pool water temperature.
-Check the pool water temperature.
Note:Re-start the chlorine generator after chemistry must be properly balanced
Note:
Re-start the chlorine generator after chemistry must be properly balanced
M4 Screw
Use screw-driver to unscrew
Swing pendulum bar several
rate
times (to check if the bar
moves smoothly; if not please
re-install flow rate sensor;
switch may not work if the
flow rate sensor did not install
properly)
Use screw-driver to unscrew
Making sure flow rate sensor is installed
properly; put cell back to cell vessel and
tighten nuts as the figure shows above
10
16
Take out cell cap and cell from
the cell vessel
Flow
Sensor
Rate

Werbung

Kapitel

loading

Diese Anleitung auch für:

Saltcontrol pool