Feed the wire electrodes (1) into wirefeeders "1" and "2"
5
Shift the mains-switches of power sources "1" and "2" into the "0" position
6
On both wire electrodes, set a suitable stick-out for the diameter of wire
7
being used
Shift the mains-switches of power sources "1" and "2" into the "I" position
8
Use the "Gas-test" button and the gas-supply pressure regulator to set the
9
shielding-gas flow rate
Die Taste Gasprüfen befindet sich
-
bei den Stromquellen am Bedienpanel
-
beim VR 1500 an der Drahtvorschub-Vorderseite
IMPORTANT!
-
The "Gas-test" button is located on the operating panel (on the power
sources)
-
The "Gas-test" button is located on the front of the wirefeeder (on the VR
1500)
Shift the mains-switches of power sources "1" and "2" into the "0" position
10
Position the welding torch (set up the robot)
11
Shift the mains-switches of power sources "1" and "2" into the "I" position
12
Check the TimeTwin Digital parameters:
13
-
Parameter t-C must be present on both power sources
-
Parameter P-C must be "On" on both power sources
Check the LHSB link
14
Welding begins when the respective start-up signal is given by the robot con-
15
trol
IMPORTANT! For detailed information on each of the operations involved, please
see the documentation that comes with the individual components.