Fig. 4.2:
4.2.5 Steps to take after completing the
tests on the safety equipment
Remove the mobile cut-off device to ensure that the power
supplies remain interrupted!
Remove the electrical bridges that were set to perform the
tests.
Re-insert plug –N0-J17 (for coil of 4-way valve)
Remove the control panel including the cable from –N0-
J15
Close motor protection switch -Q1 and -Q3
Re-connect dummy plug -XS0 correctly
Close the switch box correctly
Close the covering panels correctly.
A vapour leakage tightness check then needs to be per-
formed again.
1
2
3
Fig. 4.3:Closing the lower covering panels
Reset the operating mode on controller -N1 back to the
state it was originally in before starting the tests
EN-16
1
2
3
452167.66.43-EN · FD 0008
Maintenance instructions LA 60P-TUR
4.3 Checking the vapour leakage
tightness of the switch box
4.3.1 Closing the switch box
Close the switch box with a cover and 10x screws + sealing
washers each
Replace any faulty sealing washers: 452167.41.25
Ensure that the screws are tightened evenly cross-wise
The seal of the washer should spring up slightly, but should
not be compressed excessively. (approx. 4.5 Nm)
3
5
10
7
2
9
4.3.2 Measuring tools
The following measuring tools are required for the negative
pressure tests:
4.3.2.1Testo 510i differential pressure gauge
4.3.2.2femor vacuum pump
1
8
6
4
www.glendimplex.de