3. Receiving the product

3.1 Transporting the product

The pump can be transported and stored in vertical
or horizontal position. Make sure it cannot roll or fall
over. Make sure that the received product
corresponds to the order. In case of damage or
missing parts, inform the transport company or the
manufacturer immediately.

3.2 Handling and lifting the product

All lifting equipment must be rated for the purpose
and checked for damage before lifting the pump. The
lifting equipment rating must not be exceeded. The
pump weight is stated on the nameplate.
WARNING
Crushing hazard
Death or serious personal injury
Do not stack pump packages or pallets
on the top of each other when lifting or
moving them.
Always lift the pump by its lifting
bracket or by a forklift truck, if the
pump is fixed on a pallet. Never lift the
pump by the power cable, hose or
pipe.
CAUTION
Sharp element
Minor or moderate personal injury
Wear protective gloves when opening
the pump package.
Keep the cable end protectors in storage
for later use.
WARNING
Crushing hazard
Death or serious personal injury
Make sure your hand cannot get
caught between the lifting bracket and
the hook.
WARNING
Crushing hazard
Death or serious personal injury
Make sure the hook is fixed to the
lifting bracket properly.
Always lift the pump by its lifting
bracket or by a forklift truck, if the
pump is fixed on a pallet.
Make sure that the lifting bracket is
tightened before lifting the pump.
8

4. Mechanical installation

The compact design makes the pumps suitable for
both temporary and permanent installation. The
pumps can be installed on an auto-coupling system
or on a ring stand to the bottom of the pit.

4.1 Installation requirements

Pump installation in pits must be carried
out by specially trained persons.
DANGER
Electric shock
Death or serious personal injury
It must be possible to lock the main
switch in position 0. Type and
requirements are specified in EN
60204-1.
DANGER
Electric shock
Death or serious personal injury
Make sure there is at least 3 m free
cable above the maximum liquid level.
Maintenance and service work must be
carried out when the pump is outside the
pit. For safety reasons, all work inside pits
must be supervised by a person outside
the pit.
WARNING
Crushing hazard
Death or serious personal injury
Make sure the lifting bracket is
tightened before lifting the pump.

4.2 Installation on auto-coupling

Pumps for permanent, vertical installation in a pit can
be installed on a stationary auto-coupling unit.
Make sure that the pipes are installed
without the use of undue force. No loads
from the weight of the pipes must be
carried by the pump. Use loose flanges to
ease the installation and to avoid pipe
tension at the flanges.
Do not use elastic elements or bellows to
connect the pipes.
In some installations, a plinth is required
beneath the auto coupling to ensure the
correct installation of the pump.