Proceed as follows:
1.
Position the fixing bracket on the wall and, making sure that it is perfectly horizontal with a level,
mark the position of the holes.
2.
Drill the fixing holes with a D.10 drill.
3.
Fix the bracket to the wall and check that it is level.
4.
Make sure that the bracket is securely fixed to the wall.
5.
Position the AQUAPROF unit as indicated in the diagram.
6.
Use the 4 vibration dampers provided between the bracket and the wall (2 vibration dampers)
and between the tank and the wall (2 vibration dampers) to reduce the transmission of vibrations
to the wall.
4.2 Overflow connection
Proceed as follows:
1.
Remove the front cover of the AQUAPROF system
2.
Connect the DN50 discharge pipe to the overflow pipe of the system (see fig. 01 point 13)
3.
make sure that the discharge pipe has an incline that will guarantee the normal flow of possible
discharges.
4.
Connect the discharge to the sewerage system.
5.
If the incline of the discharge pipe is insufficient, install a lifting station in order to guarantee the
discharge.
4.3 Mains water pipe connection
Proceed as follows:
1.
Connect the mains water supply pipe to the hose with the ring nut illustrated in the diagram using
the appropriate seal (see fig. 01 point 2).
2.
Check that the float valve moves freely and that it is correctly positioned within the mains water
tank (see fig .01). The float should be able to move freely and remember to replace the lid of the
tank.