5

Installation check

After completing the installation, the following must be checked:
ƒ Wiring for completeness, short-circuit, and earth fault
ƒ Supply of the internal fan (only 500 V types)
ƒ Power connection:
ƒ Motor connection in correct phase relation (direction of rotation)
ƒ Incremental encoder (direction of rotation), if any
EDKVF9383 DE/EN/FR 1.0
– the bridge position depends on the mains voltage applied
– Supply via terminals L1, L2 and L3 (direct mains connection)
Note!
The installation check is followed by commissioning. Further information can
be obtained from the System Manual for the 9300 vector frequency inverter.
Read the System Manual carefully before you switch on the controller!
ƒ
Carry out the commissioning steps in accordance with the System Manual!
ƒ
If you use the "safe standstill" function, check the function of the circuit!
ƒ
Tip!
Current documentations and software updates for Lenze products can be
found on the Internet in the "Downloads" area under
http://www.Lenze.com
Installation check
5
83