3.4
Initial start-up
•
Make sure that no foreign bodies or impurities are present in the grease separator.
•
Close all discharge valves <25, 26, 27 and 44>.
•
Make sure that the valve on the sludge return pipe <45> (option) is open.
•
Fill the entire grease separator fully with water (up to the plant overflow at overflow <35>).
•
Basic version only (without ventilation valve <36>): Ventilate the grease separator; to do so, open the grease
discharge valve <27> until no air but rather water is visible in the discharge hose <48>.
•
Perform a pressure test; to do so:
• Open the sludge trap <23> maintenance port.
• Lock both the drainage <35> and the supply lines <16> with suitable means.
• Fill the grease separator fully
• Restore the functionality of the drainage <35> and supply lines <16>
1)
Fill up to 2 cm below the maintenance opening on the sludge trap
with water, and ensure that there are no leaks.