3
Assembly
3.1
Recommendations for installation location/operation
– Room with good ventilation and an even installation surface.
– Room temperature of at least 15° C.
– Tiled floor with drainage point.
– Hot water supply
– Room height must be at least 30 cm higher than the height of the grease separator, so that the maintenance
ports can be opened during cleaning work.
– Free working space, of at least 1 m, all around the grease separator, and 60 cm above the plant.
– Supply with calming stretch of min. 1 m (gradient 1:50). Transition from on-site fall pipe to the calming stretch
fitted with 2x 45° bends
– If the supply line is longer than 5 m, it must be ventilated separately.
– Foreign bodies (cutlery, crown caps, mustard sachets, bones, etc.) may interfere with the separation process,
the disposal and may damage the sludge return pipe (option).
– When incurred coarse materials a coarse filter in front of the separator must be connected in order to protect
the system from improper operation
– On-site lay pipelines with 30 cm distance from the mixer motor <39>, so that the free access for maintenance
is possible.
3.2
Installation instruction
3.2.1 Comfort shaft construction
1) Reduction in the risk of complete drainage of siphons and odour traps. Reduced air entry and airflow and reduced formati-
on of odours and scum in the separator.
Assembly
.
1
52 / 80
fig. [6]
V 1.0