05 - Preparation for installation
The installation must be carried out after disconnecting the electrical power by turning off
the upstream circuit breaker. Verify the absence of voltage using a multimeter.
05.1 - Package contents
1
The package contains:
1. Duo
2. Installation plate
3. Screws Ø 5 x 45mm (x4)
4. Dowels Ø 8 x 40mm (x4)
5. Screws M5 x 100mm (x2)
6. Installation manual
05.2 - Equipment needed
To install Duo, the following equipment is required but not provided:
1. Screwdriver
2. Torx T10 screwdriver
3. Crimping pliers for terminals and RJ45 (for Power Manager installation)
4. Spirit level
5. 5x eyelet terminals with a section greater than 16 mm² if needed
06 - Installation
The equipment's power supply must remain turned off during this entire phase. Failure to comply with these instructions may
cause serious damage to people and property, and even lead to death.
The following images are for illustrative purposes and may not show all the internal components present in the product.
IEC EN 60364-7-722 or equivalent national standards provide additional requirements for the electrical installation
dedicated to powering the product. If Duo is installed in a publicly accessible location, it must be protected with a surge
protection device (SPD). The SPD does not need to be part of the charging station, nor does it need to be «dedicated»
2
3 4 5
8
6
9
7. Serial card and PUK card
8. 16 mm² terminal blocks
9. Pry tool for disassembly
10. RFID cards (x3)
11. Opening keys (x4)
7
10
11
EN
9.