MACHINE INSTALLATION
The installation is to be carried out exclusively by qualified specialists, according to the
following instructions and in compliance with valid laws and local regulations.
4.1 Preparation for installation
• Place the machine on an even and stable surface.
• Never place the machine on hot surfaces.
• Place the machine on a water-proof surface, as the machine may at some point leak
water.
4.2 Electrical connection
• Make sure that the local main voltage supply corresponds to the information given on
the type plate on the front panel of the espresso machine.
• Make sure that you use the correct power plug for your country.
• Plug the machine into a grounded socket only and do not leave it unattended.
• Do not roll or bend the power cord.
• Do not use an extension cord / do not use a multiple socket.
5
FIRST USE
Read the instruction manual carefully prior to operating the machine.
Prior to starting the machine, check if:
• the steam and hot water valves are closed.
• the machine is switched off. (Power switch in the vertical position.)
• the power cord is disconnected.
• the drip tray is inserted accurately.
• the machine is placed on a water-resistant surface.
Now you can start up your machine:
1. Take down the cup warming tray. Take out the water tank and rinse it thoroughly.
2. Fill the water tank with fresh water deficient in lime, place it back into the machine and put back the
cup warming tray.
3. Plug the machine into an electrical outlet.
4. Turn the machine on by placing the metal switch in the upper position. The green control lamp and the
PID display will come on and a pump noise will be heard. If there is still a pump noise, the filling of the
steam/ hot water boiler is still being completed.
Fill mode
The PID-display indicates "FIL". Now position the brew lever upwards for at least 30 seconds at a time
to fill the coffee boiler. The display indicates the time in seconds.
Move the lever back into the lower position. The "FIL" display turns off.
5. If the pump stops and the PID display turns off while the boilers are filled, you have to refill fresh water
in the water tank. If there is enough water in the water tank again, the pump starts to operate again.
6. As soon as both boilers are filled with water, the pump will become quiet. Both boilers are now being
heated in succession whereby the coffee boiler has priority.