Herunterladen Inhalt Inhalt Diese Seite drucken

Operation Test; Delivery Of The System - Olimpia splendid NEXYA S5 E DUAL Hinweise Für Die Verwendung Und Pflege

Vorschau ausblenden Andere Handbücher für NEXYA S5 E DUAL:
Inhaltsverzeichnis

Werbung

Verfügbare Sprachen
  • DE

Verfügbare Sprachen

  • DEUTSCH, seite 149

6 - OPERATION TEST

The operation test must be carried out only after completing the following procedures:
- Electrical safety checks;
- Check for gas leakage;
- Check that the valves on the gas side and on the liquid side (high or low pressure) are completely open.
Carry out the operation test as described below:
The operation test must be carried out for at least 30 minutes.
a. Connect the unit to the mains supply.
b. Press the ON/OFF key to switch the unit on; press the MODE key to scroll between the functions below,
one at a time:
• COOL – Select the lowest possible temperature
• HEAT – Select the highest possible temperature
Leave each function active for 5 minutes.
During the operation test, carefully check that no one of the points of connection of
the coolant pipes shows any leakage.
c. At the end of the operation test, if all the checks listed in the table below have a positive result, proceed
as follows:
• Use the remote control to take the unit back to its normal operating temperature.
• Use insulating tape to wrap the points of connection of the coolant pipes located inside and that have
been exposed during installation of the internal unit.
If ambient temperature is lower than 17°C, the cooling function (COOL) does not ac-
tivate. In this case, use the manual control as described in its respective paragraph.
Table of the checks to be carried out:
List of the checks to be carried out
Absence of electric leakage
The unit is correctly earthed
All the electric clamps are correctly covered
The internal and external units are firmly installed
All the points of junction are free from leakage
Water flows correctly out of the drainage pipe
All the pipes have been insulated correctly
The unit works correctly in cooling mode
The unit works correctly in heating mode
The ventilation slits of the internal unit rotate correctly
(vertically and horizontally)
The internal unit responds to the remote control

6.1 - DELIVERY OF THE SYSTEM

When all checks and controls regarding the correct operation of the plant have been completed, the installation
technician must illustrate the following to the purchaser:
- the basic operational features,
- the plant switch-on and switch-off instructions,
- the normal use of the remote control,
- the first practical advice for routine maintenance and cleaning.
YES
NO
External (2):
Internal (2):
EN - 31
NEXYA S5 E

Werbung

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Nexya s5 e trialNexya s5 e quadriNexya s5 e pentaNexya s5 e duct multi

Inhaltsverzeichnis