3.10
Installing the cable conduit
- Bring the cable conduit (DN70) up to the cable duct <41>
(DN50) on the drain body and fit it.
For changes of direction use max. 45° bends.
3.11
Installing the upper section
Depending on installation depth, the upper section (insertion depth of the
upper section <3>) must be cut to length or given recesses
<67> for the pipe connections which are routed into the drain body
<1> at the side.
The upper section <3> may only be extended using a maximum
of 2 extension sections,so that technicians can still reach down to
the drain body for maintenance purposes.
- Insert the sealing gasket <37> grease-free into the groove on the
drain body <1>.
- Grease the sealing lips of the sealing gasket <37>.
- Push the upper section <3> into the drain body and align it.