7.3. Initial fi lling "without water conditioning"
7.3.1. Preparation
Once mounted, the All-in-One+ Connect can be put into operation.
•
Close the isolating valve of the connecting flange.
Initial commissioning can only be
carried out in this state!
•
Open the drinking water supply line to the All-in-One+ Connect
and establish the cold water pressure.
•
Open the SYR App, select the All-in-One+ Connect,
click on "Einstellungen" (settings)
on „Erstbefüllung" (initial fi lling)
and again on „Erstbefüllung" (initial fi lling)
The isolating valve of the All-in-One+ Connect opens!
•
Vent the All-in-One+ Connect via the draw-off valves upstream and downstream.
draw-off valve,
upstream
7.3.2. Setting parameters
Start the App, select the All-in-One+ Connect if applicable and click on "Einstellungen" (set-
tings). You may now enter the basic settings.
Water conditioning is deactivated when delivered!
,
.
draw-off valve,
downstream
13