Installation and operating manual
The load limiting device must not react when the hoist is loaded
to the maximum working load.
Load the load lifting equipment with the maximum working
load.
Raise until the load lifting equipment hangs freely.
The load limiting device must not react when lifting the load.
If the load limiting device reacts:
Lower the load to the ground.
Insert an 8 mm, 150 mm-long Allen key into the setting
screw (3).
Tighten the setting screw (3) one half turn.
Raise the load again.
The load limiting device must not react when lifting the load.
If setting screw (3) was adjusted, repeat the test with the maxi-
mum overload.
Load the load lifting equipment with the calculated overload.
Raise the load.
The load limiting device must react and stop the UP travel of
the hoist within the first 10 cm.
Tighten the brass screw (2).
Replace the blanking plugs (1) and secure with red sealing
wax.
Type series X 2050 P
See Fig. 16.
Load the load lifting equipment with the calculated overload.
Raise the load.
The load limiting device must react and stop the UP travel of
the hoist within the first 10 cm.
If the load limiting device does not react:
Remove the blanking plug (1).
Loosen the lock nut (5) with the socket wrench.
Insert a screwdriver into the setting screw (3).
Screw in the setting screw (3) until the load limiting device
reacts.
Lower the overload to the ground.
Raise the overload again.
The load limiting device must react. Otherwise repeat the
procedure.
The load limiting device must not react when the hoist is loaded
to the maximum working load.
Load the load lifting equipment with the maximum working
load.
Raise until the load lifting equipment hangs freely.
The load limiting device must not react when lifting the load.
If the load limiting device reacts:
Lower the load to the ground.
EN-22
Insert a screwdriver into the setting screw (3).
Screw the setting screw (3) out by one half turn.
Raise the load again.
The load limiting device must not react when lifting the load.
If setting screw (3) was adjusted, repeat the test with the maxi-
mum overload.
Load the load lifting equipment with the calculated overload.
Raise the load.
The load limiting device must react and stop the UP travel of
the hoist within the first 10 cm.
Tighten the lock nut (5) with the socket wrench.
Replace the blanking plugs (1) and secure with red sealing
wax.
15.6 Ordering spare parts
Spare parts lists can be obtained from your supplier or directly
from TRACTEL Greifzug GmbH.
The details needed to place the order are listed on the separate
component's nameplates, see 'Nameplate and warning signs /
application restrictions' on page 7.
The required information is e.g.:
Rope drive:
Article no., tirak™ model / Tractel
model, rope diameter, serial number
Motor:
Article no., Motor model
Brakes:
Article no., Type and coil voltage of the
brake
Electrical controls:
Number of the circuit diagram
Ropes:
Rope diameter, construction, length,
packing
16
Disposal and environmental
protection
The equipment is made from recyclable materials. If the equip-
ment is later scrapped, it must be disposed of correctly. The
national versions of the waste legislation directive 2008/98/EC
apply within the European Union.
The manufacturer is obliged to take back and dispose of specific
electrical and electronic components in accordance with Directive
2002/96/EC. The following symbol is used on the nameplate of
such components to identify them:
®
G919.6 - 07/2012

Werbung

loading