Mounting
S Remove the load cell dummy without the mounting base with thrust piece
by lifting lightly and withdrawing to one side (for pendulum bearing version,
with pendulum bearing)
S Insert the load cell with the thrust piece and, if necessary, the pendulum
support, apply the enclosed grease to the load introduction parts.
S Slowly lower the tank. The thrust piece above the load cell must center in
the centering flange of the upper module plate without suffering damage.
S Vertically align the module by inserting or removing the five 1‐mm‐thick
spacer plates above the thrust piece of the load cell (see Fig. 4.2)
S Mount and adjust the anti‐liftoff device by inserting spacer plates
underneath such that an air gap of about 1 mm results with the tank empty.
S First adjust and then lock the horizontal stops. The U‐shaped bracket
accounts for the stiffness of the stops and has to be fastened with the stop
screws. Please refer to the Specifications in Chapter 7 for the maximum
permissible horizontal shifts (distance from the stops). The stay rods
already have been adjusted at the factory to ensure that the load introduc
tion parts are aligned with the load cell in the rod direction. Should a read
justment prove necessary, the rod end bearings subsequently have to be
carefully locked.
Notes for adjustment of the horizontal stops
Horizontal movability is ensured by the rubber‐metal or pendulum bearing. The
horizontal stops should be adjusted in compliance with the maximum permissi
ble horizontal shift (see chapter 7 on page 22).
Notice
Precautions during operation:
S Deposits such as dirt or corrosion particles from the tank can falsify
measurement results.
S The limits for movability and loading capacity specified in the Specifications
must not be exceeded.