When installing and adjusting the Portegra2 and/or associated components, ensure
to cut off the power supply to the entire system. Danger of Death!
5.1.1
For the correct distance between the Unistrut
5.1.2
Space the provided nuts (4/Fig. 9) along the Unistrut
(see shipping carton).
5.1.3
Install the mounting plate to the nuts along the Unistrut
lock washers (2/Fig. 9), and washers (3/Fig. 9) and level with a block level, secure the screws
5.1.4
Apply Loctite
®
Please, proceed to 5.3, „Installing the ceiling column to a mounting plate".
Selection of appropriate installation hardware and its torque value is sole responsibility of the structural
holes for the mounting plate, see template Fig. 10a/10b (for a Siemens installation Fig. 10c).
5.2.2
Proceed with the drilling according to the template Fig. 10a/10b (for a Siemens installation Fig. 10c),
and the mounting hardware requirements set by the structural engineer.
engineer, and level with a block level. Use shims if necessary (not included in package).
engineer and check again the horizontal positioning with a block level.
Installing a Portegra2 column to a MAVIG mounting plate
rails, please see Fig. 10a, 10b and 10c.
®
rails in intervals of 350 mm
®
rails using the M10x35 screws (1/Fig. 9),
®
®