Herunterladen Inhalt Inhalt Diese Seite drucken

Scope Of Delivery - Solplanet SOL APOLLO Serie Schnellinstallationsanleitung

Vorschau ausblenden Andere Handbücher für SOL APOLLO Serie:
Inhaltsverzeichnis

Werbung

Verfügbare Sprachen
  • DE

Verfügbare Sprachen

  • DEUTSCH, seite 14
The installation requires at least
an area of 230 mm x 360 mm.
230mm
1
The installation height is between 1400 and 1600
mm (from the floor to the bottom of the EV charger
housing).
4
III. Scope of delivery
2
A solid and an even support
surface, e.g. concrete or masonry,
must be available for mounting.
2
1400-1600mm
A minimum clearance of 200 mm
from other equipment or objects
must be maintained.
3
The installation location must be freely accessible.
5
Energy meterX1
ENGLISH

Werbung

Inhaltsverzeichnis
loading

Inhaltsverzeichnis