Checking the Contents
of Packing

Unpacking Unitom-2

Placing Unitom-2

2

Unitom-2

Instruction Manual

1. Getting Started

In the packing box you should find the following parts:
1
Fork spanner, 30 mm, for changing the cut-off wheel
1
Grease gun, for lubrication of tilting frame bearings
2
Cover plugs for threads for cutting tables
0
1
Drain angle, 45
0
1
Drain angle, 90
1
Outlet hose 2 m
for connection to external cooling unit
2
Hose clamps, 35-60 mm
1
Set of Instruction Manuals
Remove the wooden block holding the spindle using a 17 mm
spanner.
Insert the two cover plugs delivered with the machine in the
threaded holes.
Unitom-2 should be placed on the optional Struers Table Unit, or a
table which is able to carry a weight of min. 200 kg.
Adjust the table height using the screws in the table legs. It is
important that the table and Unitom-2 are level. Place Unitom-2 on
the table. If the machine is not horizontal, you must adjust the height
for each corner, as follows:
Loosen the upper 13 mm nut under the corner screw.
Adjust the lower 8 mm nut with a spanner.
Fasten the upper 13 mm nut again.
Repeat the adjustment for each of the other three corners until
Unitom-2 is levelled.