Transport, Assembly, Putting into Operation and Decommissioning

Transport

4
Transport, Assembly, Putting into Operation and
Decommissioning
4.1
Transport
The delivered conveyor system with the length of up to 19.5 ft (6 m) is completely assembled, wired and set
so that it is ready for operation.
Conveyor systems with the length of more than 19.5 ft (6 m) will be delivered segments that have to be
assembled.
When loading, use only hoists and load lifting devices approved for appliances 1,5 times heavier than the
conveyor system to be lifted. Only the transport vehicles may be used that are approved for the weight of the
appliance.
According to the valid purchase contract, the scope of delivery is specified in the shipping documents
attached to the delivery item.
4.2

Assembly

Conveyor systems with the length of more than 6 m will be delivered segments that have to be assembled.
4.2.1

Assembly of segments

ATTENTION
ATTENTION
INFO
After packing material is removed, you can set up the conveyor system.
Perform the following work steps when assembling the segments of the conveyor system:
§
Before assembling make sure that the floors are level and even and the conveyor system is level.
§
You can uniformly adjust the height of the conveyor system by means of the screw feet. Adjust
deviations with a spirit level in the cross direction. Normally, the height is 35.5'' (900 mm).
§
When assembling begin with the end of the belt. When doing this, place the first segment on the
marked position.
§
Screw the segment under the next part of the belt. When doing this, the first person should hold the
segment while the second person is pushing the next part of the belt on to the connector of the
segment the first person is holding.
§
Put together the edges of the segments so that they are flush and screw them together from below.
§
Continue with the assembly as described above.
4330053_A5
Injury to persons and/or damage to property
There is a risk that parts of the conveyor system fall down during the
assembly. This can result in injuries to persons and damage to property.
Ask for help when assembling the segment and work at least in pair.
Damage to property
Do not place the segments onto the floor with the surface facing down, since
they can get scratched or damaged.
Use a suitable piece of material to place the segments.
Disposal of packing material
The packing consists of recyclable materials and can be disposed of
appropriately. Thereby, the different materials are to be separated and
disposed in an environmentally compatible manner. In any case, the local
bodies responsible for disposal are to be involved for this purpose.