Install the regulator at an angle to the breather

LEAK CHECK

Serious burns to the skin or damage to property.
Do not use an open flame to check for leaks.
Leak check before start-up
Before start-up, check the product connections for leaks!
1. Close all shut-off fittings on the connected devices.
2. Slowly open the withdrawal valve or the gas cylinder valve(s).
3. If there is a safety device (e.g. UPSO between the tank and the connected device(s),
open this during the leak check (see START-UP OPSO / UPSO).
4. Spray all connections with a foam producing substance according to EN 14291
(e.g. leak detector spray, Part no. 02 601 00).
5. Bubbles will form in the foam producing substance if there are any leaks.
If you cannot stop the leaks, you must not use the product.
Test connector option
A leak tester can be connected to the test connector for
pressure and leak tests on the outlet side. First, loosen the
set screw in the test connector. When you have used it,
tighten the set screw again and check for leaks again. See:
Before start-up, check the product connections for leaks.

START-UP OPSO / UPSO AND RESTARTING OPSO, OPSO/UPSO

After the product has been ASSEMBLED and LEAK TESTING has been carried out
successfully, it is immediately ready for operation.
Only RESTARTING: If the safety overpressure shut-off valve OPSO or OPSO/UPSO has
responded, which is shown in RED on the visual indicator - take the following steps:
1. Close the gas withdrawal valve, check that connected devices are closed.
2. Vent the pressure regulator  loosen the screw connection on the outlet side
3. Ventilate the inlet pressure  loosen the connection on the inlet side
4. Tighten all connections again.
5. After elimination of defects, open the gas withdrawal valve.
Artikel-Nr. 05 288 50 m
Risk of burning or fire
If more bubbles form, re-tighten the connections (see ASSEMBLY).
Behälterregler-Kombination PS 25 bar
We recommend that you install the
pressure regulator type BHK 052 and
type BHK 052B at an angle to the
breather
and
condensation to flow away better.
. This allows
.
.
25 / 182

Werbung

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Bhk 052 upsoBhk 052bBhk/k

Inhaltsverzeichnis