8. Start-Up

Never let the pump run dry for a long time of period,
as it will destroy the pump (danger of overheating).
Before starting the pump station make sure that all isolat-
ing valves are open and check that the unit runs satisfac-
torily.
Make sure that the correct phase sequence was proofed
at the 3-ph models (see 6.3.).
Turn the operation switch into the position "Auto".
In combination with the pneumatic level control the pump
starts aud stops according to the liquid level in the tank.

9. Maintenance and Repair

In case of a defect of the pump, a repair shall be car-
ried out only by the manufacturer or through an authorized
workshop. Modifications of the pump must be confirmed
by the manufacturer. Only Vogel spare parts shall be
used.
In accordance with the product liability law we point
out that we shall not be liable for damages caused by our
product due to unauthorized repair by persons other than
the manufacturer or an authorized workshop or due to the
use of spare parts other than original Vogel parts. The
same product liability limitations are valid for accessories.
Before maintenance or repair disconnect the pump
from the power supply to avoid accidental starting of the
pump!
Before maintenance or repair make sure that all rotat-
ing parts stand still!
Before carrying out maintenance and service, the
pump must be thoroughly flushed with clean water. Rinse
the pump parts in clean water after dismanteling.
At pump types with oil chamber an overpressure can
escape with loosening of the oil chamber control screw.
Screw only when pressure balance took place.
Pumps running under normal operation conditions should
be inspected at least once a year. If the pumped liquid is
very muddy or sandy or if the pump is operating continu-
ously, the pump should be inspected every 1.000 operat-
ing hours.
For long and trouble-free operation of the pump, following
points should be checked regularly:
- Nominal current (A): Check with amp-meter.
- Pump parts and impeller: Check for possible wear.
Replace defective parts.
- Ball bearings: Check the shaft for noisy or heavy opera-
tion (turn the shaft by hand). Replace defective ball bear-
ings. A general overhaul of the pump is usally required in
case of defective ball bearings or poor motor function.
This work must be carried out by an authorized
service workshop.
- Cable entry: Make sure that the cable entry is watertight
and that the cables are not bent sharply and/or pinched.
Additionally at pump types with oil chamber:
- Oil level and oil condition in oil chamber:
Put the pump in horizontal position, so that the screw of
the oil chamber is above (at larger pumps: one of both
screws). Remove the screw and infer a small quantity of
oil. The oil becomes greyish white like milk if it contains
water. This may be the result of defective shaft seal.
In this case leave the condition of the shaft seals by a
VOGEL Service to examine.
The oil should be replaced after 3000 operating hours.
Oil type: Shell Tellus C22: Used oil is to be disposed ac-
cordingly.
Servicing Contract
For a regular expert execution of all necessary mainte-
nance and inspection we recommend the conclusion of a
servicing contract by our VOGEL Service.