5.2 Installation of the charging column
5.2.1 Preparing a new foundation
The operator / owner of the charging system is responsible
for the secure installation of the charging system according
to the following specification.
9 0 0
Fig.: 6. Formwork (dimensions in mm)
Observe separate foundation plans on the website:

https://www.chargeupyourday.com/
Prepare the foundation:
f Excavate the foundation hole with the specified
dimensions.
f Insert the rectangular shaft elements 2 as permanent
formwork.
f Route the supply line 1 and optional the control lines in
an empty pipe 4 into the formwork.
f Close the opening 3 of the empty pipe with expanding
foam to avoid leakage of the concrete.
To achieve optimum strength, we recommend the
MENNEKES bed plate set available separately.
10
6 0
0
1
2
3
4
1
Fig.: 7. MENNEKES bed plate set
f Install the bed plate set 1.
f Insert the bed plate set in the form work.
f Rout the supply line 2 and optional the control lines
through the opening of the base plate.
f Align the bed plate set.
f Insert a foundation earth electrode 3 according to
DIN 18014 (e.g. band-iron). Comply with local regulati-
ons!
1
Fig.: 8. Concrete placing the foundation
f Cast the lower two thirds of the foundation with
concrete of class C20/25.
f Allow the concrete to set.
f Align the base plate 1 horizontally with locking screws.
2
3