C
Rope
Rope length
9130 mm
A
5560 mm
B
10730 mm
C
3960 mm
D
2.10.2.2
Installation of the columns
1. Transport the columns to the installation site.
2. Move each column towards the respective end of the cross beam until it is stopped by the sliding block on
the cross beam.
3. Make sure all columns are positioned in the correct location. Make sure that the columns do not fall over.
Use washers if necessary.
4. Slide down the safety racks in each column. Make sure that the rack slides through the groove of the sliding
blocks.
5. Feed the adjustment rack through the top of the column and secure it to the safety rack with the M20 nuts.
6. Make sure that all nuts are correctly installed.
® Copyright ATH-Heinl GmbH & Co. KG / All rights reserved / Misprints and technical changes reserved
90
1
2
Release date: 02.06.2023 / Product manufacturer ATH-Heinl GmbH & Co. KG
D
D
A
C
A
B
2
1

Werbung

loading