2.6 Installation example
➍
➀ KESSEL Aqualift F Compact Lifting Station
➁ Extension section with central flange
➂ Pressure pipe set with flexible pressure hose
➃ Ventilation to roof
➄ Pressure pipe should be increased to at least size DN 70 immediately
after the pressure pipe loop above the backwater level
2. Installation / 3. Commissioning
➋
3. Commissioning
Caution
Commissioning of the system should only be
handled by a qualified professional.
Before commissioning the system:
- Rinse and clean all inlet pipes
- Rinse and clean the Aqualift F tank
- Check all connections for leaks
- Check all instructions / requirements in the
control unit user manual
- Fill the Aqualift F tank with water and check for
proper operation of the pressure sensor
- Follow chapter 4 of this manual.