Transport, storage, placement and
17 / 21

initial setup

5.

Transport, storage, placement and initial setup

This chapter provides information about the scope of delivery, transport, storage, placement
and initial setup of the machine. This chapter is intended for the maintainer of the machine.
5.1.

Transport and storage

No special transport equipment is required. The machine weighs 500 kg.
The machine is equipped with forklift tubes. This makes it simple to move the machine with a
forklift.
For vertical lifting, the machine is equipped with a lifting eye.
Make sure that the machine is horizontal and stable during transport.

5.2. Placement of the machine

Make sure that the machine is horizontal and stable during use.
5.3. Initial setup
Check the oil level in the oil reservoir of the hydraulic unit. The oil level must be between 2 and
3 cm under the top of the reservoir. Top off if necessary. For the required oil type, see
section 4.7.
Connect the machine to the mains supply.
A 3-conductor mains cable is required.
The machine is equipped with the required male/female plug connection. A 3-conductor mains
cable is required. The required supply voltage is 230 VAC. For the location and construction of
the plug connection, see figure 4.2-1.
After connection to the mains, the machine is ready for use.