Measures to be implemented
Visual inspection and check of all electrical
connections.
Function test of the insulation monitoring.
Checking AC and DC voltages.
Checking the starting behaviour.
Function test of the display, the status LEDs
and the keys.
Visual inspection of the unit labelling (sticker,
type plate and warning notices) and replace if
necessary.
Documentation of the operating environment
and the unit with a camera.
66

Decommissioning

Taking the Inverter Out of Operation

8
Interval
12 months
8.1
12 months
1. Release AC disconnector and DC switch.
12 months
2. Wait 5 minutes until the inverter is discharged.
12 months
3. Dismantle electrical connections.
12 months
4. Dismantle communication lines and accessories if
necessary.
12 months
5. Loosen the hexagon socket screw on the inverter
bracket.
6. Using two people, carefully lift the inverter out of the
12 months
inverter bracket.
8.2
▷ If possible, pack the inverter in the original carton
or use an equivalent carton that is suitable for loads
of more than 60 kg.
8.3
▷ Store inverters in a dry place with an ambient tem-
perature between -25 and +70 °C.
Decommissioning
Taking the Inverter Out of Operation

Packing the Inverter

Store Inverter

REFUsol 50K-3T
982081 | 03 | 2021-03

Quicklinks ausblenden:

Werbung

Kapitel

Inhaltsverzeichnis
loading

Inhaltsverzeichnis