A - Mounting Of The Condensation Drain Device In The Vertical Version; B - Mounting Of The Condensation Drain Device In The Horizontal Version; Rotation Of Connections - Olimpia splendid Bi2 Air TR Hinweise Für Die Verwendung Und Pflege

Gebläsekonvektoren
Inhaltsverzeichnis

Werbung

Verfügbare Sprachen
  • DE

Verfügbare Sprachen

  • DEUTSCH, seite 109
- If possible, make condensation liquid flow out directly in a gutter or in a "white water" drain.
-
In case of drainage in the sewerage system, it is advised to create a siphon to prevent the perception of
bad smells towards the rooms. The curve of the siphon must be lower than the condensation collection
basin.
-
If condensation must be drained inside a container, the latter must remain open to the atmosphere and
the pipe must not be immersed in water, avoiding problems of adhesiveness and counter pressures whih
would hinder free outflow.
- If a difference in level which would hinder condensation outflow must be overcome, it is necessary to
install a pump (accessory kit).
In any case, please consult the specific instructions in the condensation disposal pump kit.
It is still opportune, at the end of installation, to check for correct outflow of condensation liquid
by pouring water in the collection basin very slowly (approximately 1/2 l of water over approxi-
mately 5-10 minutes).
2.7.a - Mounting of the condensation drain device in the vertical version (fig.10)
a. Connect a pipe (16) for liquid outflow to the drainage junction (15) of the condensation collection basin.
b. Lock it adequately.
c. Check that the drip edge extension (17) is present and installed correctly (only for models SLR/SL
200-400-600-800-1000).
2.7.b - Mounting of the condensation drain device in the horizontal version (fig.11)
For mounting of the horizontal basin on SL versions, please refer to the instructions contained in the
corresponding optional kit.
a. Cut, under the side cover corresponding to the condensation drain pipe outlet, the precut area (18).
b. Reposition the side cover.
Make sure the machine is perfectly levelled once installed, or with a slight in-
clination towards the direction of the condensation drain;
Insulate the delivery and return pipes well up to the entrance of the machine,
so as to prevent condensation dripping out of the collection basin itself;
Insulate the condensation drain pipe of the basin for its whole length.

2.8 - ROTATION OF CONNECTIONS

The described operations and their images refer to a machine with connections to the left on which the rotation
of the connections on the right side is necessary. If you have at your disposal a machine with connections to
the right with the need of rotation to the left, the sequence of operations is the same, only the images must
be considered as specular.
For connection of the electrical components, it is necessary to use the specific optional kit.
EN - 11