11. Commissioning

11.1 Initial start-up

1.
2.
3.
DCE 11/13
DCE 11/13 H
4.
5.
°C
40
30
6.
20
DCE 11/13
DCE 11/13 H
f Fill the appliance by running the tap until the pipework and
f
appliance are free of air. Open the draw-off valve several
times.
f Activate the electronic safety switch (AE3). On delivery, the
f
electronic safety switch is in the tripped position.
f Only for the DCE 11/13 | DCE 11/13 H: Insert the temperature
f
selector plug into the "set temperature" PCB. Note the align-
ment of the wires.
f Fit the appliance cover by positioning it and pressing against
f
it until the locking hooks at the top and bottom click into
place. Check that the locking hooks have clicked into place.
f Switch the mains electrical power ON.
f
f Only for the DCE 11/13 | DCE 11/13 H: Turn the temperature
f
selector to its left-hand and right-hand end-stop.
f Carry out a tightness check.
f
f Tick the selected connected load and rated voltage on the
f
type plate. Use a ballpoint pen to do this.
f Check the function of the appliance.
f
www.stiebel-eltron.com
≥ 60 s
°C
40
30
50
50
60
20
60

11.2 Appliance handover

f Explain the functions of the appliance to the user. Show the
f
user how to operate the appliance.
f Make the user aware of potential dangers, especially the risk
f
of scalding.
f Hand over these instructions.
f

11.3 Recommissioning

Material losses
!
Following an interruption to the water supply, recommis-
sion the appliance by carrying out the following steps.
This will prevent destruction of the bare wire heating
system.
f Disconnect the appliance from the power supply by removing
f
the fuses/tripping the MCBs.
f Open the tap for one minute until the appliance and its up-
f
stream cold water inlet line are free of air.
f Switch the mains electrical power back ON again.
f
f See chapter "Installation / Commissioning".
f

12. Shutdown

f Disconnect the appliance from the mains at the MCB/fuse in
f
the fuse box.
f Drain the appliance (see chapter "Installation /
f
Maintenance").

13. Installation options

13.1 Adjustable connected load

f Plug in the coding card in accordance with the selected con-
f
nected load.
DCE 11/13| DCE 11/13 RC| DCE 11/13 H |
13kW
11kW
27

Quicklinks ausblenden:

Werbung

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Dce 11/13 rcDce 11/13 h

Inhaltsverzeichnis