MAINTENANCE / RECOMMENDATIONS
• Maintenance should only be carried out by a qualified person. A yearly maintenance is recommended.
• Ensure the machine is unplugged from the mains, and then wait 2 minutes before carrying out maintenance work. Inside,
voltages and currents are high and dangerous.
• Remove the casing 2 or 3 times a year to remove any excess dust. Take this opportunity to have the electrical connections checked by a qualified
person, with an insulated tool.
• Regularly check the condition of the power supply cable. If the power cable is damaged, it must be replaced by the manufacturer, its after sales
service or an equally qualified person to prevent danger.
• Ensure the vents of the device are not blocked to allow adequate air circulation.
• Check that the torch does not have any cracks or exposed wires.
• Check that the consumables are installed properly and not worn.
Air filter maintenance :
Purge of the filter tank :
• Unplug the air supply.
• Loosen the valve in the lower part of the filter tank by turning it anticlockwise.
• Push the tap upwards to drain the water from the tank.
• Tighten the valve at the bottom of the filter tank by turning it clockwise.
Removing the filter element :
• Disconnect the air supply.
• Take hold of the tank and unscrew it from the body by turning it anticlockwise.
• The filter element (white) can be blown out or replaced depending on its condition.
Reassembling the filter element :
• Put the filter element back in the tank, check the presence of the O-ring in the upper part.
• Screw the tank back onto the body by turning it clockwise.
INSTALLATION – PRODUCT OPERATION
Only qualified personnel authorised by the manufacturer should perform the installation of the welding equipment. During the installation, the
operator must ensure that the machine is disconnected from the mains.
MACHINE SUPPLIED WITH
4 m
Pneumatic fittings
6 m
Starting kit
DESCRIPTION
NEOCUT is a three-phase Plasma cutting & gouging machine, it will allow:
- Cutting on all metal types
- Gouging on all metal types
- Marking on all metal types
These 3 processes require the use of appropriate consumables as well as compressed air or nitrogen.
EQUIPMENT DESCRIPTION (FIG. 1 - PAGE 2)
1-
Display screen
2-
Adjustment knob
3-
Earth clamp connection socket
4-
Plasma torch connector
CNC 1 analog (optional, ref. 039988) or CNC 2 digital (optional, ref.
5-
064737) connector installation door
Installation door for digital retrofit CNC 3 connector
6-
(option, ref. 068957)
NEOCUT 105 / 125
NEOCUT 105
Ref. 063044
8 mm + 10 mm
-
-
Accessories supplied with the generator are designed to be used on this machine only.
Ref. 063112
Ref. 067431
8 mm + 10 mm
8 mm + 10 mm
7-
Transport handles.
8-
Replacement for pneumatic connector
9-
Power supply cable
10-
On/off switch
11-
Filter
NEOCUT 125